Unpriced bill of quantities
A bill of quantities (BoQ) is an important document prepared by a quantity surveyor (or cost consultant) which itemises the type, form and amount of material that will be required on a project, including quantities of labour and other items. Quantities may be measured in number, length, area, volume, weight or time and are known as ‘measured quantities’.
A BoQ may be priced, in that prices are given by suppliers for each item. The sort of considerations that might be considered when pricing work include current costs of materials, machinery hire and transport, wages, overhead expenses associated with administration and so on.
In contrast, an ‘unpriced bill’ is a BoQ that is essentially a template: it breaks down the work required on a project into exact tasks but has no measured quantity (or price) by each task. The information is arranged into a form that is suitable for direct pricing by a supplier, describing the individual items to be priced and the numbers, amounts or quantities of each required for the project.
It is up to the company tendering for the project to insert against each task what it will charge the client to complete that task. This priced bill of quantities constitutes the tenderer's offer. It is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
The preparation, by the client’s consultants, of an unpriced bill of quantities means all tendering contractors will be pricing the same quantities (rather than taking-off quantities from the drawings and specifications themselves), and so provides a fair and accurate system for tendering. It also makes it possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
[edit] Related articles on Designing Buildings Wiki
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.